NEWS RELEASE
COLORADO DEPARTMENT OF TRANSPORTATION
****************************
Construction impacts for the week of Oct. 15, 2023
Berthoud to Johnstown
The southbound I-25 closure planned for Saturday, Oct. 14, has been rescheduled due to supplier issues. The closure is now planned for Saturday, Oct. 21, 8 p.m. to 7 a.m. and Saturday, Oct. 28, 9 p.m. to 5 a.m., between Colorado Highway 402 and Colorado Highway 60 while crews install a new overhead signage structure and a message board across the highway, north of mile point 253.
- Southbound I-25 traffic will exit at CO 402, turn right and travel west to US 287, turn south and continue to Colorado Highway 66, turn left and travel east to re-enter southbound I-25 at mile point 243.
- Traffic on CO 402 intending to travel south to Larimer County Road 16 via I-25 will be diverted to County Road 7 southbound.
Sunday, 5 a.m. to noon, the southbound I-25 off-ramp at CO 60 will be closed to allow crews to place a new light pole near the ramp. The southbound I-25 right lane will also be closed from 5 a.m to 9 a.m. for lane striping.
- Southbound I-25 traffic intending to exit at Johnstown will continue south to mile point 250, turn and travel north to mile point 252.
Monday through Thursday, 9 p.m. to 5 a.m., there will be nightly southbound I-25 right lane closures between CO 60 and Colorado Highway 56 for sign structure installation.
Saturday, Oct. 21, 6 a.m. to 6 p.m., the southbound I-25 on-ramp at CO 60 will be closed to install an asphalt curb near the ramp.
- Traffic intending to enter southbound I-25 will travel north to CO 402, turn and enter I-25 south.
Johnstown to Fort Collins
To perform roadway finishing work, various intermittent ramp closures will take place next week:
Intermittent southbound I-25 on- and off-ramp closures at CO 392 will take place from:
- 9 p.m. to 5 a.m. nightly, Sunday and Monday
Southbound I-25 off-ramp traffic will continue south on I-25 to Exit 259/Crossroads Boulevard, turn east, and continue onto northbound I-25. Continue north on I-25 to Exit 262/CO 392.
Southbound I-25 on-ramp traffic will go north on I-25 to Exit 265/Harmony Road and turn left. Continue back onto southbound I-25.
Intermittent closures of the northbound I-25 off-ramp to CO 402 will take place from:
- 9 p.m. to 5 a.m. nightly, Tuesday and Wednesday
Northbound off-ramp traffic will continue north on I-25 to Exit 257/US 34. Traffic will exit, turn left, and continue onto southbound I-25 to Exit 255/ CO 402.
Intermittent closures of the northbound I-25 on-ramp from CO 402 will take place from:
- 9 p.m. to 5 a.m. nightly, Tuesday, Wednesday and Friday
Northbound I-25 on-ramp traffic will go south on I-25 to Exit 254/US HWY 60. Traffic will exit, turn left, and continue onto northbound I-25.
Intermittent closures of the northbound I-25 off-ramp to US 34 will take place from:
- 9 p.m. to 5 a.m. nightly, Tuesday through Friday
Northbound I-25 off-ramp traffic will continue north on I-25 to Exit 259/Crossroads Boulevard. Traffic will exit, turn left, and continue onto southbound I-25 to Exit 257/US 34.
Intermittent closures of the northbound I-25 on-ramps from eastbound and westbound US 34 will take place from:
- 9 p.m. to 5 a.m. nightly, Tuesday through Thursday
Northbound I-25 on-ramp traffic will go east on US 34 to Centerra Parkway and turn north. Continue to Crossroads Boulevard and turn west. Continue to the northbound I-25 on-ramp.
Intermittent closures of the southbound I-25 on- and off-ramps at Prospect Road will take place from:
- 9 p.m. Thursday to 5 a.m. Friday
Southbound I-25 on-ramp traffic will go north on I-25 to Exit 269/Mulberry Street and continue back onto southbound I-25.
Southbound I-25 off-ramp traffic will go south on I-25 to Exit 265/ Harmony Road and turn left. Continue back onto northbound I-25 to Exit 268/ Prospect Road.
Intermittent closures of the northbound I-25 off-ramp to Crossroads Boulevard will take place from:
- 9 p.m. Friday to 5 a.m. Saturday
Northbound I-25 off-ramp traffic will continue north on I-25 to Exit 262/CO 392 turn west and continue onto southbound I-25. Continue south on I-25 to Exit 259/Crossroads Boulevard.
Daytime single lane closures on southbound I-25 will take place between Mulberry Street and Mountain Vista Road daily from 9 a.m. until 3 p.m., Monday through Thursday.
Single lane closures on I-25 between CO 402 and Prospect Road will take place nightly, 9 p.m. to 5 a.m., Sunday through Friday.
Firestone Mobility Hub
Daytime work, Monday - Saturday, 7 a.m. - 7 p.m.
Southbound I-25
- Southbound traffic will be shifted to the right 24/7 through October.
- Caution: Watch for workers on foot and operating equipment.
- Trucks will merge with left lane traffic from the left shoulder. No lane changing in work zone.
Northbound I-25
- Trucks will exit the highway from the left lane. Do not follow trucks into the work zone.
- Lanes narrow slightly through the work zone - Watch for wide vehicles.
East I-25 Frontage Road
- The construction crew will be setting a southbound traffic shift into the middle turn lane.
- Flaggers will be in place to guide traffic.
Southbound Frontage Road/I-25 On-Ramp
- Construction crews will be working on the left shoulder behind barrier on the left lane and shoulder.
- One lane of through traffic.
Additional Information
For specific lane closures and traffic impacts from Sunday, Oct. 15 - Saturday, Oct. 21, please use this interactive map on the project webpage. To display full details on the traffic impacts, please click on any of the color-shaded areas on the map to see the full details. A pop-up on the left side of your screen will outline the details of the lane closures.
Construction activities are weather-dependent and subject to change. Please watch for construction vehicles entering and exiting mainline I-25 and obey all posted signage in construction zones. Your safety and the safety of our crews is our highest priority.
The I-25 North Express Lanes Project provides a Courtesy Patrol during commute hours (6 to 9 a.m. and 3:30 to 6:30 p.m.) to assist with disabled vehicles within the Project limits from Johnstown to Fort Collins.
About the Project
Communities along the I-25 North corridor are expanding rapidly, contributing to major economic growth in northern Colorado. The Colorado Department of Transportation is supporting this growth by delivering the expansion of I-25 North. Improvements are currently underway along I-25 between Berthoud and Fort Collins (with more to come from Mead to Berthoud).
This project brings economic, environmental and quality of life benefits for northern Coloradans by:
- Making safety improvements to reduce the number of crashes and fatalities.
- Decreasing travel time and increasing trip reliability.
- Reducing emissions and improving freight efficiency.
- Improve congestion and safety.
- Rebuilding aging and obsolete infrastructure.
- Improving bicycle, pedestrian and transit connectivity.
Stay Connected
Project Webpage: www.codot.gov/projects/northi25
Hotline: 720-593-1996
Email: [email protected]
Road Conditions: COtrip.org
COtrip Planner App: bit.ly/COtripapp
Project Travel Alerts: bit.ly/COnewsalerts
Lane Closures: bit.ly/laneclosures
****************************