Construction impacts for the week of Oct. 15, 2023

Construction activities are weather-dependent and subject to change
20231016-colorado-construction-projects

NEWS RELEASE
COLORADO DEPARTMENT OF TRANSPORTATION
****************************
Construction impacts for the week of Oct. 15, 2023

Berthoud to Johnstown

The southbound I-25 closure planned for Saturday, Oct. 14, has been rescheduled due to supplier issues. The closure is now planned for Saturday, Oct. 21, 8 p.m. to 7 a.m. and Saturday, Oct. 28, 9 p.m. to 5 a.m., between Colorado Highway 402 and Colorado Highway 60 while crews install a new overhead signage structure and a message board across the highway, north of mile point 253.

  • Southbound I-25 traffic will exit at CO 402, turn right and travel west to US 287, turn south and continue to Colorado Highway 66, turn left and travel east to re-enter southbound I-25 at mile point 243.
  • Traffic on CO 402 intending to travel south to Larimer County Road 16 via I-25 will be diverted to County Road 7 southbound.

Sunday, 5 a.m. to noon, the southbound I-25 off-ramp at CO 60 will be closed to allow crews to place a new light pole near the ramp. The southbound I-25 right lane will also be closed from 5 a.m to 9 a.m. for lane striping.

  • Southbound I-25 traffic intending to exit at Johnstown will continue south to mile point 250, turn and travel north to mile point 252.

Monday through Thursday, 9 p.m. to 5 a.m., there will be nightly southbound I-25 right lane closures between CO 60 and Colorado Highway 56 for sign structure installation.

Saturday, Oct. 21, 6 a.m. to 6 p.m., the southbound I-25 on-ramp at CO 60 will be closed to install an asphalt curb near the ramp.

  • Traffic intending to enter southbound I-25 will travel north to CO 402, turn and enter I-25 south.

Johnstown to Fort Collins

To perform roadway finishing work, various intermittent ramp closures will take place next week:

Intermittent southbound I-25 on- and off-ramp closures at CO 392 will take place from:

  • 9 p.m. to 5 a.m. nightly, Sunday and Monday

Southbound I-25 off-ramp traffic will continue south on I-25 to Exit 259/Crossroads Boulevard, turn east, and continue onto northbound I-25. Continue north on I-25 to Exit 262/CO 392.

Southbound I-25 on-ramp traffic will go north on I-25 to Exit 265/Harmony Road and turn left. Continue back onto southbound I-25.

Intermittent closures of the northbound I-25 off-ramp to CO 402 will take place from:

  • 9 p.m. to 5 a.m. nightly, Tuesday and Wednesday

Northbound off-ramp traffic will continue north on I-25 to Exit 257/US 34. Traffic will exit, turn left, and continue onto southbound I-25 to Exit 255/ CO 402.

Intermittent closures of the northbound I-25 on-ramp from CO 402 will take place from:

  • 9 p.m. to 5 a.m. nightly, Tuesday, Wednesday and Friday

Northbound I-25 on-ramp traffic will go south on I-25 to Exit 254/US HWY 60. Traffic will exit, turn left, and continue onto northbound I-25.

Intermittent closures of the northbound I-25 off-ramp to US 34 will take place from:

  • 9 p.m. to 5 a.m. nightly, Tuesday through Friday

Northbound I-25 off-ramp traffic will continue north on I-25 to Exit 259/Crossroads Boulevard. Traffic will exit, turn left, and continue onto southbound I-25 to Exit 257/US 34.

Intermittent closures of the northbound I-25 on-ramps from eastbound and westbound US 34 will take place from:

  • 9 p.m. to 5 a.m. nightly, Tuesday through Thursday

Northbound I-25 on-ramp traffic will go east on US 34 to Centerra Parkway and turn north. Continue to Crossroads Boulevard and turn west. Continue to the northbound I-25 on-ramp.

Intermittent closures of the southbound I-25 on- and off-ramps at Prospect Road will take place from:

  • 9 p.m. Thursday to 5 a.m. Friday

Southbound I-25 on-ramp traffic will go north on I-25 to Exit 269/Mulberry Street and continue back onto southbound I-25.

Southbound I-25 off-ramp traffic will go south on I-25 to Exit 265/ Harmony Road and turn left. Continue back onto northbound I-25 to Exit 268/ Prospect Road.

Intermittent closures of the northbound I-25 off-ramp to Crossroads Boulevard will take place from:

  • 9 p.m. Friday to 5 a.m. Saturday

Northbound I-25 off-ramp traffic will continue north on I-25 to Exit 262/CO 392 turn west and continue onto southbound I-25. Continue south on I-25 to Exit 259/Crossroads Boulevard.

Daytime single lane closures on southbound I-25 will take place between Mulberry Street and Mountain Vista Road daily from 9 a.m. until 3 p.m., Monday through Thursday.

Single lane closures on I-25 between CO 402 and Prospect Road will take place nightly, 9 p.m. to 5 a.m., Sunday through Friday.

Firestone Mobility Hub

 Daytime work, Monday - Saturday, 7 a.m. - 7 p.m. 

Southbound I-25

  • Southbound traffic will be shifted to the right 24/7 through October. 
  • Caution: Watch for workers on foot and operating equipment.
  • Trucks will merge with left lane traffic from the left shoulder. No lane changing in work zone.

Northbound I-25

  • Trucks will exit the highway from the left lane. Do not follow trucks into the work zone.
  • Lanes narrow slightly through the work zone - Watch for wide vehicles. 

East I-25 Frontage Road

  • The construction crew will be setting a southbound traffic shift into the middle turn lane.
  • Flaggers will be in place to guide traffic.

Southbound Frontage Road/I-25 On-Ramp 

  • Construction crews will be working on the left shoulder behind barrier on the left lane and shoulder.
  • One lane of through traffic.

Additional Information

For specific lane closures and traffic impacts from Sunday, Oct. 15 - Saturday, Oct. 21, please use this interactive map on the project webpage. To display full details on the traffic impacts, please click on any of the color-shaded areas on the map to see the full details. A pop-up on the left side of your screen will outline the details of the lane closures.

Construction activities are weather-dependent and subject to change. Please watch for construction vehicles entering and exiting mainline I-25 and obey all posted signage in construction zones. Your safety and the safety of our crews is our highest priority.

The I-25 North Express Lanes Project provides a Courtesy Patrol during commute hours (6 to 9 a.m. and 3:30 to 6:30 p.m.) to assist with disabled vehicles within the Project limits from Johnstown to Fort Collins.

About the Project

Communities along the I-25 North corridor are expanding rapidly, contributing to major economic growth in northern Colorado. The Colorado Department of Transportation is supporting this growth by delivering the expansion of I-25 North. Improvements are currently underway along I-25 between Berthoud and Fort Collins (with more to come from Mead to Berthoud).

This project brings economic, environmental and quality of life benefits for northern Coloradans by:

  •  Making safety improvements to reduce the number of crashes and fatalities.
  •  Decreasing travel time and increasing trip reliability.
  •  Reducing emissions and improving freight efficiency.
  •  Improve congestion and safety.
  •  Rebuilding aging and obsolete infrastructure.
  •  Improving bicycle, pedestrian and transit connectivity.

Stay Connected

Project Webpage: www.codot.gov/projects/northi25
Hotline: 720-593-1996
Email: [email protected]
Road Conditions: COtrip.org 
COtrip Planner App: bit.ly/COtripapp
Project Travel Alerts: bit.ly/COnewsalerts
Lane Closures: bit.ly/laneclosures

****************************